Developer Guide

How to get a water and sewer capacity check
Pre-development enquiries in England, Wales, Scotland and Northern Ireland

A capacity check is called a pre-development or pre-planning enquiry. You make it to the water company that owns the network your site would connect to. This guide explains what to send, what you get back, and the 2026/27 fees that companies publish.

Developer GuideWater capacity checkSewer capacity checkPre-development enquiryWater connections

Water Industry Hub does not carry out capacity checks. A capacity check comes from the water company that owns the public water mains or sewers. This page points you to each company's own process and its published 2026/27 fee.

Not sure which company serves your site? Check by postcode.

What a capacity check is

Before you buy land, submit a planning application or design your site services, you can ask the local water company whether its network can supply your development with water and take away its foul and surface water flows. Water companies call this a pre-development enquiry or pre-planning enquiry. Some offer separate water and wastewater enquiries; others answer both in one response.

The charging documents published under Ofwat's rules for companies in England define the response the same way. In the words of Portsmouth Water's, South Staffs Water's and SES Water's 2026/27 documents, it is "a report by the Water Company in response to a Pre-Planning Enquiry" that confirms whether the development can be supplied with water, the capacity within the wastewater network, and whether reinforcement work will be needed.

Planning permission does not settle the question. Scottish Water states that planning permission granted by a local authority "does not secure the provision of water and waste water services" and "does not guarantee that there is sufficient network capacity available for new connections".

What you get back

Each company describes its response in its own charging document or website. Examples from the 2026/27 documents:

A response is not a permanent promise. Scottish Water says any response at pre-development stage "is not a guarantee of water or wastewater capacity" and that you secure capacity through a formal water and/or wastewater application. Responses also expire: United Utilities gives a validity period of 6 months for a water pre-development enquiry response and 12 months for a wastewater one, and Yorkshire Water charges £380 to renew an expired water pre-planning enquiry response where your requirements have not changed.

Step by step

1. Find the right company

In England and Wales the water supplier and the sewerage company for a site can be two different companies. Use our postcode checker, then confirm on the company's own website. Make a water enquiry to the water supplier and a wastewater enquiry to the sewerage company.

2. Prepare what the company asks for

Requirements differ by company, so read the application form first. Examples from the companies' own pages and documents:

Southern Water's fees are banded by the number of units (0 to 50, 51 to 250, and >251 as its document shows them), and for water Southern recommends a point of connection application for sites with over 500 units. Northern Ireland Water has separate single-unit and multi-unit fees.

3. Pay the fee and submit

Several companies state that the fee is paid with the application and is non-refundable, for example United Utilities and Welsh Water. Check whether the published figure includes VAT: the table below shows the basis each document gives.

4. Wait for the response

Where a company states a reply time, we show it in the table. Examples: Welsh Water says it will respond "within 21 days"; Portsmouth Water says it will acknowledge your application within 5 days and provide the report within 21 days of receiving a complete application; South East Water says it has 21 calendar days to provide a budget (capacity) estimate. Where the document we checked does not state a time, the table says "Not stated": ask the company.

2026/27 pre-development enquiry fees by company

Fees for 2026/27 (1 April 2026 to 31 March 2027), checked on 8 November 2026 against each company's own published charging document or developer page, named in the last column. Page numbers are PDF page numbers. Fees are per enquiry unless stated.

CompanyWaterWastewaterVAT basisReply time stated in the document or page citedSource (2026/27)
Water and sewerage companies, England and Wales
Anglian Water£213 non-domestic capacity report; £421 water pre-planning report (modelled)£320 foul tier 1 (feasibility); £960 foul tier 2 (detailed desktop); £960 surface waterVAT added where payable21 days for a Tier 1 feasibility report (how-to-apply page); not stated for the other reportsDeveloper Charging Arrangements 2026-2027 (Anglian Water Development Services), Table 3, p13
Dŵr Cymru Welsh Water£201.44 per written pre-planning response, covering water and wastewater+ VAT21 days (pre-planning page)Developer Services Schedule of Charges 2026-27, p7
Hafren Dyfrdwy£178.66£197.60 (both: £280.60)Excludes VATNot stated in the document citedDevelopment Services Charging Arrangements 2026/2027, p18
Northumbrian Water£207£1,440Excludes VATNot stated in the document citedDeveloper services charging arrangements 2026/27 (version 3), p13 and p42
Severn Trent£178.66£197.60 (both: £280.60)Excludes VATNot stated in the document citedCharges for new water and sewerage connections 2026-27, p12 to p13
South West WaterNo charge for the pre-development enquiry service; further work charged if neededExcludes VAT21 calendar days for a point of connection enquiryNew Connections and Developer Services 2026/27 (v1.2), p9 to p10
Southern Water£183 (0 to 50 units); £550 (51 to 250); £735 (>251)Foul: £183 / £550 / £735. Surface water: £367 / £1,101 / £1,469Generally excludes VAT; Southern's application fee list shows £219.60 inc VAT for 0 to 50 unitsNot stated in the document citedNew Connections Services Charging Scheme 2026-27, p24 and p38; Developer Services List of Application Prices 26/27
Thames Water£170£195+ VAT at the applicable rateNot stated in the document citedCharging arrangements for new connection services 2026/27, p4
United Utilities£261.46£479.78Excludes VATNot stated (response valid 6 months water, 12 months wastewater)New connections and developer services charges scheme 2026/2027, p14
Wessex WaterPre-planning enquiry response free. Site-specific: odour modelling verification £1,078; fly nuisance risk assessment £484; a fee may apply for network modelling where a site is neither allocated in a Local Plan nor has development management approvalExcludes VATNot stated in the document citedNew connection services charging arrangements 2026-2027, p30
Yorkshire Water£496 (renewal of an expired response £380)£557; additional assessment for complex sites £198 per hourExcludes VATNot stated in the document citedTables of charges, New Connection Charging Arrangements 2026/2027, p5 and p19
Water supply companies, England (no sewerage service: make the wastewater enquiry to the sewerage company for the site)
Affinity Water£0 (new mains pre-planning enquiry and self-lay point of connection enquiry are free of charge)n/aExcludes VATNot stated in the document citedNew Connections Charging Arrangements 2026/27, Table 5.2, p12
Bristol Water area (South West Water)No charge for the pre-development enquiry service; further work charged if neededn/aExcludes VAT21 calendar days for a point of connection enquiryCharging Arrangements for New Connection Services 2026-27 (V1.1), p8; VAT p46
Bournemouth Water area (South West Water)As South West Water: no chargen/a (South West Water's document says to use Wessex Water's or Southern Water's arrangements)Excludes VAT21 calendar days for a point of connection enquirySouth West Water, New Connections and Developer Services 2026/27 (v1.2), p3 and p9
Essex & Suffolk Water (Northumbrian Water)£207n/aExcludes VATNot stated in the document citedDeveloper services charging arrangements 2026/27 (version 3), p13
Portsmouth Water£227, plus a £249 hydraulic assessment fee that Portsmouth adds to every pre-development enquiry invoice (£476 in total)n/aExcludes VATReport within 21 days of a complete applicationDeveloper Services Charging Arrangements 2026-27, p22; pre-development page
South East Water£344.89 (pre-development enquiry, budget)n/aInclusive of VAT at 20%21 calendar daysCharging Arrangements for New Connection Services 2026/2027 (V2), Appendix 2, p83; p32
South Staffs Water and Cambridge Water£115 (listed as "Developer enquiry/speculative enquiry/Self Lay POC application")n/aExcludes VATNot stated in the document citedDeveloper Services charging arrangements 2026 to 2027, Table 1, p19
SES WaterSee the company's charges page. No pre-development enquiry fee is listed in the 2026/27 document we checked.--Developer Services Charging Arrangements 2026/27
Scotland and Northern Ireland
Scottish WaterSee the company's Applying page and Your Charges Explained 2026-27. No PDE fee is listed in that document; that document lists an application fee of £113.70 per application for connection applications.-Not stated in the document citedYour Charges Explained 2026-27, p17
Northern Ireland WaterPre-development enquiry (includes records request): £79 + VAT (£94.80) single unit; £340 + VAT (£408) multi-unit. Water and wastewater impact assessments are listed separately at £209 + VAT (single unit) and £2,459 + VAT (multi-unit) each.Shown + VAT and inc VATNot stated in the document citedSummary Scheme of Charges 2026/2027, p1

The list of companies follows Ofwat's register of regional water and sewerage undertakers and regional water supply undertakers in England and Wales (Ofwat, Licences and licensees page, opened 8 November 2026), plus Scottish Water and Northern Ireland Water. Bristol Water, Bournemouth Water, Essex & Suffolk Water and Cambridge Water are shown as supply areas because their companies' documents cover them. New appointees (NAVs) are not listed.

Fees change every year. United Utilities' document notes that "charges change on 1 April each year", and each document in the table covers the 2026/27 charging year. These 2026/27 figures apply from 1 April 2026 to 31 March 2027. Always confirm the current fee, VAT and process with the water company before you apply. Fees on this page were checked on 8 November 2026.

What happens next

New water connections and mains

Once you know the network can serve your site, you apply to the water company for the new mains and service connections. Some of this work can be done by the water company or by an accredited self-lay provider. Thames Water's 2026/27 document says self-lay providers "can carry out the majority of the work involved in laying new water pipes or diverting existing ones", known as contestable work, while non-contestable work remains Thames's responsibility.

Self-lay providers (WIRS)

Self-lay organisations working on water company networks are accredited under the Water Industry Registration Scheme (WIRS), which LRQA operates on behalf of water companies. LRQA, which operates WIRS on behalf of water companies, publishes the search for a WIRS accredited self-lay organisation. Our accreditation guide explains WIRS and related schemes. Water mains laid by a self-lay provider are adopted by the water company under an agreement made under section 51A of the Water Industry Act 1991 ("Agreements to adopt water main or service pipe at future date").

New appointments and variations (NAVs)

A NAV (new appointment and variation) is a company appointed as the water and/or sewerage undertaker for a defined area, known as an inset, such as a new development site (Portsmouth Water describes a NAV serving "your development in a defined area known as an inset"). United Utilities' 2026/27 document notes that a self-lay provider or a NAV "may carry out work that is deemed contestable, subject to suitable accreditation". Ofwat lists the appointed new appointee water and sewerage undertakers on its Licences and licensees page. Several regional companies charge separately for NAV enquiries; see their charging documents.

Sewer connections and adoption (Section 106 and Section 104)

A connection to a public sewer is made under section 106 of the Water Industry Act 1991 ("Right to communicate with public sewers"). New sewers that a developer builds for the sewerage company to adopt are covered by an agreement under section 104 ("Agreements to adopt sewer, drain or sewage disposal works, at future date"). Anglian Water's 2026/27 document offers a Pre-design Strategic Assessment that can be requested at any point before a section 104 application, to check that a proposed drainage design is suitable for adoption.

Drainage strategy and surface water

Some companies ask for your proposed drainage strategy with the enquiry; Welsh Water's 2026/27 schedule asks for "any proposed drainage strategies". In Wales, Welsh Water's pre-planning page says all new development of more than one building, or a construction area of 100m² or more, requires consent from the sustainable drainage systems (SuDS) approval body (SAB) for any new SuDS features, and recommends speaking to your local SAB before making a pre-planning enquiry about a surface water connection.

Find suppliers

Our supplier directory lists firms working in the UK water sector. If you are a self-lay provider, NAV or drainage consultancy and would like developers to find you there, contact us.

Need help with a capacity check?

You do not have to make the enquiry yourself. Northumbrian Water's developer pages, for example, have a route for people "working on behalf of someone else - eg. consultant, architect or local authority", and a separate route for self-lay providers. Check the developer pages of the company that serves your site to see who it accepts an enquiry from. Our supplier directory lists firms working in the UK water sector, including a civil engineering contractors and consultancies category. For accredited self-lay providers, use LRQA's WIRS search.

Do this work? Developers reading this guide can find suppliers in our directory. A basic listing is free. Bronze membership adds a verified profile with your contact details: £250 a year launch price (standard £349), billed annually, for firms that join by 31 March 2027.

Frequently asked questions

Who can confirm water or sewer capacity for a development?

The water company that owns the public water mains or sewers your site would connect to. You ask through its pre-development (pre-planning) enquiry. Water Industry Hub does not carry out capacity checks.

How much does a pre-development enquiry cost in 2026/27?

Each company sets its own fee: see the table above. Affinity Water, South West Water (including the Bristol and Bournemouth areas) and Wessex Water state no charge for the standard enquiry. Check whether the figure includes VAT.

How long does a capacity check take?

Where a company states a time, it is shown in the table: for example 21 days for Welsh Water and Portsmouth Water, and 21 calendar days for South East Water. Other documents we checked do not state a time, so ask the company.

Is a pre-development enquiry response a guarantee of capacity?

No. Scottish Water says its response "is not a guarantee of water or wastewater capacity" and that you secure capacity through a formal application. Responses also expire: United Utilities gives 6 months for water and 12 months for wastewater.

Who can lay the new water mains for my site?

The water company, or a self-lay provider accredited under WIRS for contestable work. LRQA, which operates WIRS on behalf of water companies, publishes the register.

Sources (all opened 8 November 2026): the 2026/27 charging documents and developer pages of Anglian Water, Dŵr Cymru Welsh Water, Hafren Dyfrdwy, Northumbrian Water (with Essex & Suffolk Water), Severn Trent, South West Water, Bristol Water, Southern Water, Thames Water, United Utilities, Wessex Water, Yorkshire Water, Affinity Water, Portsmouth Water, South East Water, South Staffs Water (with Cambridge Water), SES Water, Scottish Water and Northern Ireland Water, as named in the table; Ofwat, Licences and licensees; LRQA, WIRS search; Water Industry Act 1991, sections 51A, 104 and 106 (legislation.gov.uk).

Planning a development?

Water Industry Hub tracks tenders, frameworks and contract awards across UK and Irish water companies, and keeps a supplier directory for the sector.

Browse the Directory More Guides
The information on this page was accurate to the best of our knowledge at the time of publication. The water industry moves quickly — regulatory decisions, enforcement actions, investment figures and company positions can change. Water Industry Hub updates pages when material changes come to our attention, but we cannot guarantee that all information remains current. Always verify directly with the relevant authority or company before making commercial or procurement decisions. This content does not constitute legal, financial or regulatory advice.