Update — 5 August 2026 This framework has been relaunched. Anglian Water published a new Find a Tender notice (073419-2026, 4 August 2026) covering the same scope under the title "Major Infrastructure Planning and Consents Support, And Advisory Services" — this time valued at £58.8m (incl. VAT) with an unlimited-supplier framework structure, a request-to-participate deadline of 7 September 2026 and contracts starting 25 February 2027. These terms supersede the £83-99m / max-21-supplier figures below, which related to the original April 2026 competition. Read the updated figures and timeline →
Procurement Intelligence

Anglian Water's £83-99m Consenting Framework —
Planning Is Becoming Its Own AMP8 Category

Anglian Water is building an 8-year framework for the specialist advisers who get major infrastructure through planning — DCO applications, environmental assessment, stakeholder consultation and land agency. It's a niche corner of AMP8, but it's the corner that unlocks everything else on the delivery side. Here's what's in it, and what it signals for suppliers working the wider consenting pipeline.

£83-99m
Total estimated framework value, incl. VAT, over 8 years
21
Maximum suppliers across the framework's 5 lots
21 Aug
Estimated award decision date for the successful firms
Anglian WaterPlanning & ConsentingDCONSIPConsultancyEnvironmentalLand & Property

Most AMP8 procurement coverage focuses on the visible end of delivery — civils frameworks, MEICA contracts, sewer rehabilitation lots. Anglian Water's Major Infrastructure Planning and Consents, Support and Advisory Services framework sits well upstream of any of that. It doesn't build anything. It gets the right to build something through the planning system in the first place — and without it, the reservoirs, desalination plants and pipeline schemes that dominate Anglian's investment story can't move off the drawing board.

The framework was first flagged to the market in late November 2025, refined through several notice updates, and formally confirmed the request-to-participate window closed 22 April 2026. Anglian Water is now evaluating and expects to confirm the successful firms around 21 August 2026, with contracts starting between September and October. It's an eight-year commitment (four years firm, with options to extend to 2034), run as a bespoke Anglian Water Services Framework Agreement with NEC4 PSC/PSSC call-offs.

What's Actually in the Framework

The scope splits into five lots, each covering a distinct discipline in the planning and consenting chain:

Lot 1
Strategic Consenting Advisory Services
£13.8–17.2m
Lot 2
Consenting Leadership, DCO Application & Examination Management
£35–44m
Lot 3
Environmental Services (HRA & specialist advisory)
£1.6–2m
Lot 4
Stakeholder & Consultation Support
£13.4–16.7m
Lot 5
Land & Property Support & Advisory
£16–20m

Lot 2 — consenting leadership and Development Consent Order (DCO) application and examination management — is comfortably the largest piece, and the description makes clear why: it covers project and production management of the entire suite of DCO documents, engagement with Local Planning Authorities, and compliance through the pre-examination and examination phases under the Planning Act 2008. This is the discipline that keeps a Nationally Significant Infrastructure Project (NSIP) moving on schedule through what is usually the single biggest source of delay risk on a major scheme.

Why This Sits Separately from Anglian's Programme Delivery Partner

The notice is explicit that Environmental Impact Assessment delivery is not in scope here — that continues to be procured through Anglian's Programme Delivery Partner arrangement. What this framework buys is the specialist planning and consenting layer that sits alongside main scheme design and delivery: strategic advice on planning routes, DCO production management, HRA-specific environmental input, stakeholder engagement strategy, and compulsory purchase/land referencing. It's a reminder that on NSIP-scale water infrastructure, "delivery partner" and "consenting partner" are increasingly treated as two separate procurement tracks with two separate specialist supply chains.

Why This Matters Beyond Anglian

Anglian isn't consenting anything trivial. The framework exists to support its current and future major infrastructure programme — most visibly the Fens and Lincolnshire reservoirs, four desalination plants, the Advanced Water Recycling Centre in Colchester and the Strategic Pipeline Alliance, several of which are DPC- or SIPR-designated schemes running to the mid-2030s. Anglian's SRO Fens Reservoir project held its Market Launch Event on 29 June 2026, with Main Works Contracts procurement still being shaped — this consenting framework is the parallel track that has to keep pace with it.

The same pattern is showing up across the sector right now. Welsh Water's newly launched £556m Cwm Taf Water Supply Strategy — a DPC scheme spanning a new water treatment works near Merthyr Tydfil and an upgrade inside Bannau Brycheiniog National Park — will need exactly this kind of DCO and stakeholder consultation capability once it moves past market engagement. Thames Water's Teddington Direct River Abstraction drought-resilience scheme has already appointed Jacobs and Mott MacDonald as technical partner specifically to navigate consenting. And Scottish Water's newly opened WICS Draft Determination consultation — proposing c.£7.9bn of investment for the next regulatory period — points to a fresh wave of major scheme consenting work north of the border from 2027 onwards.

The Supply Chain Signal

Planning and consenting specialists — DCO/NSIP planning consultancies, EIA and HRA environmental advisers, stakeholder and communications agencies, and land/compulsory purchase agents — have historically sat in the shadow of the civils and MEICA primes on AMP8 coverage. As more water company capital programmes reach for NSIP-scale, DPC-designated and SIPR delivery models, planning and consenting is emerging as a distinct, framework-level procurement category in its own right, not just a sub-scope buried inside a delivery partner contract.

Timeline

27 Nov 2025
Anglian Water's planned procurement notice for the framework first published.
8 Apr 2026
Formal tender notice published, opening the competitive flexible procedure across all five lots.
22 Apr 2026
Deadline for requests to participate — the competitive window suppliers needed to be in for this round.
~21 Aug 2026
Estimated award decision date — successful firms across Lots 1-3 confirmed first, Lots 4-5 following shortly after.
Sep–Oct 2026
Contract start dates across the five lots, running to 2030 with options to 2034.

What You Should Be Doing Now

Practical Steps for Suppliers

Never Miss a Framework Award

Water Industry Hub tracks procurement notices, pipeline signals and award decisions across every major UK water operator — including the specialist consenting and advisory frameworks that rarely make headlines but drive who gets first access to the next wave of major schemes.

View Silver Membership Talk to Us First
The information on this page was accurate to the best of our knowledge at the time of publication. The water industry moves quickly — regulatory decisions, enforcement actions, investment figures and company positions can change. Water Industry Hub updates pages when material changes come to our attention, but we cannot guarantee that all information remains current. Always verify directly with the relevant authority or company before making commercial or procurement decisions. This content does not constitute legal, financial or regulatory advice.